Meghalaya
is a relatively fortunate State in the sphere of power
generation. While most of the States in the country have
serious shortages of power, Meghalaya is surplus and is
in a position to supply power to its neighbouring States
of Assam, Nagaland and Mizoram. This State, as discussed
earlier, has a Hydro and Thermal Potential of about
3000 MW and 1000 MW respectively. Out of this
potential, the State has been able to develop only
185.20 MW of hydro power so far.
TRANSMISSIONS
AND TRANSFORMATION SCHEME:
Considering the rapid growth of load demand in the
State, MeSEB formulated a scheme for taking up the
augmentation and construction work of 132KV/220KV Grid
sub-stations and transmission lines.
Due to this rapid load growth, MeSEB is facing
shortage of power in the recent time. In order to enable
MeSEB drawing its Central Sector power share from the NE
grid, strengthening of its existing network is becoming
inevitable. In view of this, numbers of transmission
schemes have been formulated and targeted to be
completed on a priority basis to meet the short-term
demand of the State. The schemes being implemented are
as follows:
A.
Construction
of the 132 KV transmission line from Sarusajai in
Assam
to Byrnihat in Meghalaya
The project cost of the line is Rs. 1045.00 lakhs
and is funded under NLCPR.
DONER at the cost of Rs. 9.78 crores approved the
project. The
Meghalaya portion of the line has been completed and
commissioned on
20-05-05
. The
Assam
portion of the line is being taken up by ASEB and the
work is in progress.
This line on completion will enable the state to
draw an additional 80 MW of power.
B.
Construction
of the 132 KV transmission line from the Me.S.E.B.
Sub-Station at Khliehriat to PGCIL Sub-Station at
Khliehriat
The project is funded under NLCPR at the
estimated cost of Rs. 286.00 lakhs.
The work is in progress.
C.
Construction
of the 132 KV double circuit transmission line from Agia
in
Assam
to Nangalbibra in Meghalaya
The revised project cost of the line is Rs.
4693.65 lakhs. The
NEC funds the project.
The forest clearance for both the Meghalaya and
Assam
portion of the line had been obtained and forwarded to
the NEC. The EFC memorandum for the construction of line
had been submitted to the NEC in January 2006.
D.
Construction
of 220 KV transmission line from Misa in
Assam
to Byrnihat in Meghalaya along with the construction of
the 220 KV/132 KV, 1 x 100 MVA at Byrnihat
The Detailed Project Report was cleared by CEA
and the work is to be executed by a Joint Venture
between Me.S.E.B. and PGCIL.
MOU for this project was signed on the
08-09-05
.
The project is scheduled to be completed by
March, 2009 and the project cost of the scheme is Rs.
243 Crores.
E.
The 132/33 KV
Sub-Station at NEIGHRIMS was commissioned on
6th May, 2005
F.
Construction
of the 132 KV/33 KV Sub-Station at Norbong, Byrnihat
The project cost of the work is Rs. 465.00 lakhs.
The work is in progress.
G.
Construction
of the 132 KV/33 KV Sub-Station at Khliehriat
The project cost of the work is Rs. 84.00 lakhs.
The work has been completed in all respect.
H.
Augmentation
of the 132 KV/33 KV Sub-Station at Nangalbibra
The project cost of the work is Rs. 85.00 lakhs.
The work involves the augmentation of the
Sub-Station from 17.5 MVA to 25 MVA and the work is in
progress.
OTHER TRANSMISSION LINE WORKS BEING TAKEN UP ARE AS FOLLOWS
A.
LILO
of 132 KV Stage IV – Sarusajai at Umtru Power Station
NEC under NEC 10th Plan at the project cost of
Rs. 3.87 crores funds this project and the work is in
progress. This
line will improve the grid network and derive optimum
benefit from the 100 MVA transformation capacity
installed at Sarusajai to cater to the demand at
Byrnihat.
B.
132
KV Leshka Khliehriat line
The project was approved for funding under ACA.
The NIT for the work is being issued and the
material procurement work is in progress.
C.
2nd
circuit of the 132 KV single circuit line from Stage III
Power Station to Stage IV Power Station
The project will be funded by NEC under the NEC
10th Plan.
The revised project cost is Rs. 458.00 lakhs and
the detailed project report had been submitted to NEC in
January, 2006. The project is scheduled to be completed
by March, 2007.
D.
Construction of the
132 KV/33 KV Sub-Station at Lumshnong with LILO
of the 132 KV Khliehriat – Panchgram line
The
DONER at the cost of Rs. 4.63 crores approved the
project. The
work has been completed as per scheduled.
This project will cater to the growing industrial
load demand around Lumshnong and will improve the
quality of domestic power supply.
SUB-TRANSMISSION AND DISTRIBUTION SCHEMES
A.
Distribution
Master Plan
This project is taken up in order to improve the
existing transmission system and to provide quality and
reliable power to the people of the state.
The project will also enable additional sale of
energy and reduce the energy losses that in turn would
generate additional revenue income to the Board.
The project is funded under NLCPR at an approved
cost of Rs. 24.00 crores.
The target date of completion of the project is
June 2006.
B.
Improvement
of power supply in Tura
The project is funded under NLCPR at an approved
cost of Rs. 12.03 crores and the work was completed in
the month of October 2005.