Leshka Project

Jaintia Hills District, Meghalaya
A Brief Profile of the Project

The Myntdu Leshka Hydro Electric Project is situated in the Jaintia Hills District of Meghalaya on the southern slopes in the foot hills adjoining to the international boundary with Bangladesh. The Project site is located in the different geological formation having diverse lithological character. The Myntdu Leshka H. E. Project is a Run of the River (ROR) scheme with envisages the utilization of the river Myntdu & its tributaries the Lamu & the Umshariang to generate about 372mu of Power through the 2 (two) units of 42 MW each. The tri-junction of the above three tributaries is called Leshka at a longitude 92015’E & latitude 25010’N.

The project area is a narrow & steep, laying between the central upland Region of Meghalaya & the plains of Bangladesh. The region is popularly known as Ri-war. The fall of the hills at many places is sudden & sharp, forming deep gorges & river valleys. It is characterized by numerous precipices, cliffs, waterfalls & beautiful platforms overlooking the plains of Bangladesh. The coming of the Project is sure to make the area a favorite destination for tourism.

The approximate road distance to the Project site is as follows:

a.

Nearest Airport

Gopinath Bordoloi International Airport , Guwahati

b.

Nearest Railway station

Guwahati

c.

Distance from Guwahati to Project site

216Km

d.

Distance from Guwahati to Shillong

100Km

e.

Distance from Shillong to Project site

106Km

f.

Nearest Sub-Division (Civil) HQ

Amlarem

g.

Nearest District HQ

Jowai

The main components of the Project include the 66m high concrete gravity dam on the 100m downstream of Leshka tri-junction. The stored water is conducted through a 3.605km long water conductor system comprising a tunnel, surge shaft, high pressure tunnel & penstock pipe to the power house on the bank of the river Lynriang housing 2 (two) machine of 42MW each.

While the investigation works of Myntdu Leshka Project were taken up, the implementing authority took special care to ensure that the Project will have the least impact on the environment and that there will be no displacement of any villages. In fact, 2 (two) Projects further upstream of Leshka near Jowai, viz. Salim & Suchen would have facilitated big storage reservoirs & much bigger projects than that one at hand which were identified by the Central Electricity Authority. The sole reason of not taking up them was that it would have submerged a large number of thickly populated villages & cultivated land.


The MYNTDU RIVER 

The Myntdu River, in its upper reaches originates, from the place Mih Myntdu at an elevation of 1372m (4500ft) & flows towards the south for a distance of about of 10Km with the steep gradient upto an elevation of about 1220m. From this point, the river takes a sharp bend towards the east & flows in that direction for a distance of about 11Km. In the next 27Km, the river gradually drops by about 595m (1950ft) & flows mostly through narrow valleys towards the south west for the first 16Km. Over the next 11Km, it flows towards the south upto an elevation of approximately 595m (1950ft) near Leshka where two tributaries of Myntdu viz. Umshariang from the west & Lamu from the east meet the Myntdu River. Leshka is named after the aforesaid tri-junction of rivers.

From Leshka, the river flows towards the south for a distance of about 6.4Km with a loop towards the south east till it meets its major tributary, the Lynriang River at an elevation of about 335m (1100ft). For the remaining 10Km of its journey towards the plains, the Myntdu river flows south with a loop to an elevation of 30.5m (100ft) near Kharkhana. Up to this portion from Leshka, the river drops by about 564m (1850ft) in a distance of 16Km offering great scope for hydro power development in two stages. Though the upper reaches of the Myntdu River below Jowai appear suitable for a good storage reservoir, it is not considered for inclusion in the project proposal because it involves submergence of large areas of cultivated land & thickly populated areas. To save the cultivable lands & villages from submergence on which the local people are solely dependent, it is proposed to construct the storage dam at suitable site in the lower reaches of the Myntdu River thereby confining the storage to the riverine channel portion only. The catchment up to the dam site is 350Sq. Km. The project components are likely to face aggressive acidic atmosphere due to high degree of acidity in the water of Myntdu river. The indiscriminate & unscientific coal mining in the catchment area has led to the high acidity in the river water. No aquatic life actually exists in the water of the Myntdu River.

The Project is located near Dawki falls in the Zone ‘V’. Thus, elaborate measures to nullify the effects of the earthquake have been undertaken in the design parameters.

CHRONOLOGY OF EVENTS

The following tables indicate the important Chronology of events for getting the Project clearance : 

Events

Year

1999

2000

2001

2002

2003

2004

Tec Clearance

Sept

Ü

 

 

 

 

 

Provisional Environment Clearance

 

Ü

 

 

 

 

 

Provisional Forest Clearance

 

 

 

Ü

 

 

 

Zero Date Of The Project

 

 

 

Ü

Nov

 

 

 

Administrative Approval Of The Board

 

 

 

 

Ü

 

 

 

Foundation Stone Laid By The Honorable President Of India

 

 

 

 

25th Oct/02

 

 

Final Forest Clearance

 

 

 

 

 

 

Ü

Date Of Formal Start

 

 

 

 

 

 

Ü

Salient Features Of Myntdu Leshka H. E. Project, Stage-I, Jaintia Hills District, Meghalaya

I       GENERAL:

 

A. Name of the Project

: Myntdu Leshka Hydro Electric Project, Stage – I.

B. Location

: Jaintia Hills District, Meghalaya

 

: Latitude-250-10’ to 250-17’

 

: Longitude- 920-15’ to 920-30’

C. (i) River

: Myntdu

    (ii) Catchments Area

: 350Sq. Km.

D. Installed Capacity

: 2 x 42 MW

E. Annual Energy Potential –

 

(I) In a 90% dependable year      

: 372.69 MKwh

(II) Firm Power in a 90% dependable year

: 14.15 MW

F. Time required for completion

: 5 (five) years from date of TEC.

G. Estimated cost of construction –

 

(A) (Jan ’99):

 

Civil   

: Rs. 181.69 Lakhs

Electrical      

: Rs. 103.67 Lakhs

Total            

: Rs. 285.36 Lakhs

H. The revised cost of the Project as on April, 2006 –

Civil Works   

: Rs. 386.91 Lakhs

Electrical & Mechanical Works

: Rs. 110.96 Lakhs

Total Cost    

: Rs. 497.87 Lakhs

II.     COST OF GENERATION

: Rs. 2.21/Kwh.

SELLING PRICE

: Rs. 3.00/Kwh.

III.     CIVIL WORK:

 

A. Leshka Dam –

 

Type  

: Concrete Gravity

Live Storage 

: 7.32M Cum

FRL

: 618.00m

MDDL

: 606.15m

Bed Level     

: 561.00m

Length:

 

(I) Overflow 

: 107.50m

(II) Non-Overflow             

: 212.10m     = 319.60

Deepest Foundation Level   

: 557.00m

Crest Level  

: 587.50m

Maximum Height

: 66.00m

Top of Non-overflow section

: 620.00m

Spillway Capacity    

: 10,440 Cumecs